HOWARD CORNES Consultant Solicitor

HOWARD CORNES Consultant SolicitorHOWARD CORNES Consultant SolicitorHOWARD CORNES Consultant Solicitor
Home
Reported Cases
About Me
Services & Fees

HOWARD CORNES Consultant Solicitor

HOWARD CORNES Consultant SolicitorHOWARD CORNES Consultant SolicitorHOWARD CORNES Consultant Solicitor
Home
Reported Cases
About Me
Services & Fees
More
  • Home
  • Reported Cases
  • About Me
  • Services & Fees
  • Home
  • Reported Cases
  • About Me
  • Services & Fees

Significant Reported Cases

Reinwood Ltd v. L Brown & Sons Ltd [2007] UKHL 12

Geldof Metaalconstructie NV v. Simon Carves Ltd [2010] EWCA Civ 667

Geldof Metaalconstructie NV v. Simon Carves Ltd [2010] EWCA Civ 667

Acting for the successful Claimant Reinwood Ltd where the House of Lords considered the issue of whether the cancellation of the certificate of non-completion under Clause 24 (of the JCT 98) by the grant of an extension of time had the effect that the employer could no longer justify a deduction of liquidated damages. Upholding the decision of the Court of Appeal, the House of Lords held that the employer’s right to deduct liquidated damages was not lost by the grant of the extension of time even if its effect was to cancel the certificate of non-completion. The cancellation of the non-completion certificate did not have retrospective effect and the employer was therefore entitled to rely on that certificate.

Geldof Metaalconstructie NV v. Simon Carves Ltd [2010] EWCA Civ 667

Geldof Metaalconstructie NV v. Simon Carves Ltd [2010] EWCA Civ 667

Geldof Metaalconstructie NV v. Simon Carves Ltd [2010] EWCA Civ 667

Acting for the successful Defendant Simon Carves Ltd  where the Court of Appeal took the opportunity to clarify the law in relation to equitable set-off in response to a claim brought by Geldof  who had separate unrelated sub-contracts with the Defendant contractor Simon Carves Ltd for both sub-contract works and the supply only of other materials on the same project. The Court of Appeal held that the  Defendant was entitled to set-off a counterclaim it had against Geldof  for the correction of defective works under the sub-contract against a claim brought by Geldof for non-payment under the supply contract, because it would otherwise be inequitable to consider one claim without the other where, in this case,  the  contracts were so closely related.

Alfred McAlpine Construction Ltd v Panatown Ltd [2001] 1 AC 518

Geldof Metaalconstructie NV v. Simon Carves Ltd [2010] EWCA Civ 667

Alfred McAlpine Construction Ltd v Panatown Ltd [2001] 1 AC 518

Acting for Ibstock Brick Ltd in the Part 19 proceedings instigated by McAlpine against thirty two of its sub-contractors in response to Panatown's claim for damages in respect of defective works. The McAlpine's appeal was allowed. The Court of Appeal held that since the employer was not party to the original contract, they had no grounds to seek damages for delay and defects, especially where the terms of the duty of care deed had already been exercised. The employer had suffered no financial loss so could not claim more than the nominal damages that were already determined by the duty of care deed.

  • Privacy Policy

Howard Cornes - Consultant Solicitor

This website is for informational purposes only. Using this site or communicating with Howard Cornes Consultant Solicitor through this site does not form a solicitor/client relationship.  This site is legal advertising.


Copyright © 2018

Cookie Policy

This website uses cookies. By continuing to use this site, you accept our use of cookies. Privacy Policy

DeclineAccept & Close